Most AI Datacenter Power Won't Arrive
19AUG
US datacenters have asked grid operators for 1,066 gigawatts of power. Wood Mackenzie projects only about 28 percent will ever get committed. The AI buildout's pipeline is mostly paper.
The mismatch is structural. Datacenter demand jumped from 23 gigawatts in 2023 to 42 in 2026, but a power plant takes 5 to 10 years to build. A datacenter takes under three.
Developers know it, so they file the same project with multiple utilities and keep whichever connection lands first. Grid queues are full of duplicates and options, not commitments.
For anyone modeling AI capacity, headline gigawatt announcements are now a vanity metric. Signed interconnection agreements are the real number - and they're a quarter of the ask.